Early shutdown of the nuclear power plant Ringhals

Vattenfall has decided to close Ringhals unit 1 and 2 earlier than previous planned by 2025. Instead, the shutdown of 1.5GW capacity is expected to occur between 2018 and 2020.

 

Ea Energy Analyses has assessed the impact on electricity prices in Denmark for the Danish Energy Agency. The Balmorel model was used to analyse the electricity prices with and without Ringhals unit 1 and 2. The analyses describes in detail which power plants will deliver the electricity instead of Ringhals.

 

The project was carried out in the spring of 2015

Last update 17-Jul-2015

Further information


Contact: Mikael Togeby

 

 

Helge Ørsted Pedersen

 

 

 

Ea Energy Analyses Frederiksholms Kanal 4, 3. th.1220 Copenhagen KDenmark Tel work+45 88 70 70 83 Fax +45 33 32 16 61

GEO: 55.675932, 12.575096